What is the handover timetable, and what compensation does the contract set if there is a delay?

Why our handover is staged, why Romania has no statutory delay compensation, and seven checks on the preliminary contract before you pay.

4 min full read · 30 sec short versionFrom: When will the villa be handed over, and what compensation does the contract give for delay? The question to ask every developer in Romania12.10.2026
The short versionSwipe →
December 2027Staged handover

Handover is staged, starting from December 2027. Each villa's date depends on its position in the project, and appears in the preliminary contract.

207/2025The law that sets no date

Romania has no fixed statutory compensation for delay, as Israel's Sale Law provides. Law 207/2025 sets no handover date or compensation either.

25%How much the developer may spend

Under Law 207/2025, advances go into the dedicated account, and the developer may spend up to 25% of the price on the structure, then up to 20% on systems.

1538Agreed compensation, no proof of damage

Article 1538 of the Civil Code lets you claim the compensation set in the contract without proving damage. Without such a clause, you have to prove everything.

6 monthsA judgment in place of the contract

If the house is ready and the developer will not sign, you have 6 months to ask the court for a judgment that takes the place of the contract.

Handover date and compensation for delay in Romania: the short answer

In our case, handover is staged, starting from December 2027, and each villa's date depends on its position in the project. As for compensation: Romania has no fixed statutory compensation for delay, as Israel's Sale Law provides. Anyone looking at property for sale in Romania should know that protection against delay lies in the preliminary contract only: a date for the specific villa, a grace period, agreed compensation and a right to cancel. Ask to see all four in writing, before any payment, with us and with any developer. The same applies if you are looking for an apartment for sale in Romania in an off-plan project.

Why we do not give a single date

The project has 29 villas, and 9 of the 29 have already been sold. Construction is progressing in stages, so one villa will be handed over before its neighbour. A single date for the whole project would have sounded better in an advert, but it would not have been true.

That is why we write "staged, starting from December 2027". We do not publish the stage table on the website, because the date that binds us is the one written in your contract, not on a marketing page. At the meeting, ask for three things: the villa's number, its stage, and the date that will be written for it in the preliminary contract.

Another fact you should know: we finance construction from our own money, with no bank financing for the build. So there is no external financing body monitoring the project on its own behalf, and your check needs to rest on three things: the contract, the dedicated account required by law, and the site itself.

What Romanian law gives you, and what only the contract gives you

In Israel, the Sale (Apartments) Law (in Hebrew) sets, in section 5A, compensation for delay without proof of damage. Romania has no such mechanism. Law 207/2025, the "Nordis law", does not set a handover date or compensation either. It protects the money, not the timetable.

What protects you Where it comes from What it gives you
A separate bank account dedicated to the project Law 207/2025 (now Article 422 of the Planning Code) Every payment out of it approved by the site supervisor
A spending cap per stage Law 207/2025 Up to 25% of the price on the structure, and after it is complete up to 20% on the building systems
A fine for moving money Law 207/2025 1% of turnover for a developer who uses the advances for another purpose
A formal notice Article 1522 of the Civil Code A written deadline, from which the breach is counted
Agreed compensation Articles 1538 and 1541 The amount in the contract, without proving damage
Cancellation or a judgment in place of the contract Articles 1550, 1552 and 1669 Return of the money, or transfer of ownership through a claim within 6 months

A handover date without agreed compensation is a statement of intent, not a commitment.

We set out the full toolkit in the article on your rights when the developer is late with handover.

What to ask to see in our contract

The preliminary contract is signed before a notary, as the law requires, and the binding specification is the one attached to the contract. Under the law, a notary may draw up a preliminary contract for a future home only after the building permit has been registered in the land register and there is an extract for the future unit. The project has a building permit, and we show it.

A handover date without agreed compensation is a statement of intent, not a commitment.

The binding wording is the one in the draft you will receive, and we put it on the table at the meeting. This is what a good answer looks like, with us and with any developer:

  • The handover date: a date for the specific villa, not "a quarter", and a grace period defined in days.
  • Compensation for delay: agreed compensation (clauza penală) as an amount per day or per month, counted from the day after the grace period.
  • Force majeure: under Article 1351, this is an external, unforeseeable event that cannot be overcome or prevented. The law allows the parties to agree otherwise, so a clause that widens the definition needs a time limit.
  • A right to cancel: after a delay of a defined period, with return of all the money by a fixed date.
  • The payment schedule: payments tied to construction stages you can see on site, into the project's dedicated account.

If any of the five is missing from the draft, ask why.

What you don't say out loud

To some buyers, "starting from December 2027" sounds like the wording of someone already planning to be late. And in the head of every Israeli who has read about Romania, Nordis is playing too, the affair in which the insolvency administrator found 212 apartments promised to more than one buyer. And at home someone asks: "And what if we pay, and wait three years for a house that doesn't exist?"

These are fair questions. The answer is not in my promise that there will be no delay. It lies in two things you can check: where your money sits at each stage, and what the contract says on the day the date passes. Under Law 207/2025, the advances go into the project's dedicated account, and from them the developer may spend up to 25% of the price on the structure, and only once the structure is finished up to a further 20% on the building systems. The money moves when the construction moves.

How to check this yourself

  1. Ask for the villa's number and its handover stage, and insist on a date in the contract, not "a quarter" and not "about".
  2. Ask for the draft preliminary contract before the second meeting, and have a Romanian lawyer acting for you read it. The company's lawyer represents the company only, not you.
  3. Check that the compensation is defined as agreed compensation (clauza penală), with an amount per day or per month. That way you will not need to prove damage.
  4. Read the force majeure clause. It should be defined and limited in time, not an open list.
  5. Check that the payment schedule is tied to construction stages, and make sure the account number in the contract is the project's dedicated account.
  6. Get an extract from the land register (ANCPI) and make sure the permit is registered and that the preliminary contract has been registered. The notary must request registration the same day, or at the latest the next business day.
  7. Visit the site, or ask for dated photos, and compare the construction stage with the payment you are being asked for.

We have gathered all the checks before signing in the Nordis law checklist, and the ten clauses that must appear in the contract in the guide to the preliminary contract.

The same question, for every seller

Anyone comparing an apartment for sale in Romania in an off-plan project with a villa from us should ask both sellers exactly the same questions. A developer who answers in writing and in numbers also answers the real question: whether they intend to meet the date.

Frequently asked questions

Is there statutory compensation for late handover in Romania?

No. Unlike Israel's Sale Law, in Romania compensation is set in the contract only. Without an agreed compensation clause, you have to prove the damage in court.

When will the villa I am buying at Compass on the Lake be handed over?

Handover is staged, starting from December 2027. You get the specific villa's stage at the meeting, and the binding date in the preliminary contract.

I bought an off-plan apartment for sale in Romania and the developer is late. What do I do?

Start with a written formal notice under Article 1522, with a deadline for performance. From there the way opens to the agreed compensation, cancellation or a lawsuit. If the house is ready and the developer will not sign, you have 6 months from the date the contract should have been signed to ask for a judgment that takes its place.

The bottom line

In Romania, the law protects your money during construction, and the contract protects the timetable. Anyone looking at property for sale in Romania needs to read both.

At the meeting, ask us exactly the question in the headline: what is this villa's date, and what does the contract say if we are late. Ask for the answer in writing. And the next question in the series is what the price does not include, and what it costs every year.

Moti Azulay, Compass Group Romania

Sources and data: Law 207/2025, Romanian legislation portal · Romanian Civil Code, legislation portal · Sale (Apartments) Law, section 5A (in Hebrew) · Land registration authority (ANCPI) · g4media, 17.11.2025: the findings of the Nordis insolvency administrator.

This article is for general information only and is not legal advice. Handover and compensation terms are set in your contract, so check them with an independent Romanian lawyer before any payment.

Now you know more.

✓ Why our handover is staged✓ What Romanian law does not give✓ Which clauses to ask for✓ How to check the extract and site
Book a meeting →

This article is general information, not legal, tax or financial advice. Consult local professionals before any transaction.