Guy's project, a residential complex in the Bucharest area, ran into the kind of delay that happens on almost every project: a main contractor who progressed more slowly than planned, and an infrastructure approval delayed by a few months at the local authority. Nothing dramatic in itself. But the kind that adds up.
Some of the buyers had already asked questions. They weren't angry yet, but they were asking. And Guy, who has been running projects in Romania for several years, knew exactly what happens when those questions don't get answered. He knew his preliminary agreements included a late-handover penalty clause, as every such agreement should: a clause meant to protect the buyer if the date passes without an extension agreed in writing. And he knew that at some point, if he didn't act, the buyers would start demanding that penalty formally. And then it would no longer be a conversation. It would be a lawsuit.
He called me on his own initiative, before I asked and before he had to. "I want to give money back to a few buyers," he said. "Before anyone asks me."
We sat down together and worked out two scenarios. In the first, Guy waits. If and when a buyer formally demands the contractual penalty, he'll pay it, but by that point the buyer will already be upset, will have consulted a lawyer, and may demand more than he's really owed to "cover the risk." In the second, he moves first, before anyone demands anything, and offers voluntary partial compensation: lower than the full penalty, but paid immediately, without lawyers, and without the buyer having to fight for it at all.
Guy chose the second scenario, and not because he's generous. He explained it in simple words: "I'm not giving the money back because I feel bad. I'm giving it back because it costs me less, and because it buys me something money doesn't always buy: a buyer who keeps telling his friends about the project, instead of telling them he had to sue me."
He approached the three buyers who were closest to boiling point, before they approached him. He offered each a fixed, immediate sum, plus a detailed and binding written update on the new schedule, with an additional commitment if that date wasn't met either. Two buyers accepted the offer immediately. The third hesitated, asked to take advice, and in the end he agreed too, after seeing that the other two had already received a fair answer.
In the end the project was delayed by a few more months beyond the original forecast. But when the apartments were handed over, Guy didn't face lawsuits, or negative reviews that could have hurt him on the next project, or lawyers on the other side. He faced a cost known in advance, which he paid on terms he set himself.
I come back to this story a lot, because it's the opposite of what people think about "giving up money." Guy didn't give up anything. He recognized he had a window, the moment between "the buyers are still just asking" and "the buyers are already suing," and acted inside it, before the window closed and the delay cost him much more.
That's not generosity. It's recognizing that in project management, and abroad in particular, sometimes the most profitable action is the one that looks least profitable at the moment you take it.
This story first appeared in Ilan Leibovitch's weekly LinkedIn column, "Two International Real Estate Stories a Week", issue of 19.9.2026, in Hebrew.
More stories: Contracts, registration and guarantees
Have a similar story?
Ilan speaks Hebrew, English and Romanian. Book a half-hour call, or send this story to someone who is about to sign.
This story is general information, not legal, tax or financial advice. Every deal is different; consult professionals before deciding.